Earned-value analysis. a project budget calls for the following

 

Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)
grammarlytutors
Calculate your essay price
(550 words)

Approximate price: $22

How it Works

1

It only takes a couple of minutes to fill in your details, select the type of paper you need (essay, term paper, etc.), give us all necessary information regarding your assignment.

2

Once we receive your request, one of our customer support representatives will contact you within 24 hours with more specific information about how much it'll cost for this particular project.

3

After receiving payment confirmation via PayPal or credit card – we begin working on your detailed outline, which is based on the requirements given by yourself upon ordering.

4

Once approved, your order is complete and will be emailed directly to the email address provided before payment was made!